Well No. 748 Kulakovskogo deposits of JSC "Samaraneftegaz"

In the period from 28 March to 6 April, works on cutting out the "window" in the production string at the well No. 748 Kulakovskogo deposits of JSC "Samaraneftegaz". The work was carried out in a column with a diameter of 168/9,0 mm. Before carrying out the main operations performed additional work to expand the internal passage diameter of zero pipe cutting. The process window in a casing is cut in the interval 1484-1487м, and podborer "pocket" on the rock of 4 meters. All work is performed in normal mode.

 